Framing

The walls are going up! This whole process took about a month.

First they put the new main level floor joists in.

Then they installed insulation.

Plywood over the insulation for the subfloor. We had all kind of leveling issues between the many remodels on this house so had to use taller floor joists for the second floor and double layer of plywood on the ground floor to make sure we didn’t have to add any little steps between the existing house and the addition.

Then they started the main floor walls.

Window framing and second level floor joists.

Framed around the foundation walls in the basement and frame the closet around the structural support posts.

Second level subfloor and walls.

Installed second floor ceiling and sub roof.

They added more walls to separate new master closet/bath with new bedroom and frame out the master bath shower and closet.

They cut out the roof to accommodate the new bedroom dormer egress window.